Thacker Pass received a Record of Decision in January 2021 from the U.S.
Department of the Interior Bureau of Land Management (BLM) and commenced
initial construction in early 2023.
Phase 1 of Thacker Pass is designed for nominal production capacity of
40,000 tonnes per year of battery-quality lithium carbonate, and
mechanical completion is targeted for late-2027.
Thacker Pass is situated at the southern end of the McDermitt Caldera,
approximately 60 miles (100 km) northwest of Winnemucca, in Humboldt
County, northern Nevada.
We are committed to engaging with our broad range of stakeholders to
responsibly develop Thacker Pass to become one of North America's largest
sources of lithium chemicals.
Project financing for Phase 1 of Thacker Pass includes a $2.23 billion
loan from the U.S. Department of Energy’s Advanced Technology Vehicles
Manufacturing Loan Program and strategic investments from General Motors
Holdings LLC and Orion Resource Partners LP. Construction of Phase 1 of
Thacker Pass is expected to create nearly 2,000 direct jobs, including
1,800 skilled contractors.